After the electrical officer came to see the job page, he said that he had to apply for expansion, an electrical officer would plant a lamp pole and pull the wires from the alley. If there was no house number, he would lose all his own power pole, so he suggested asking for the first number, but.....
The building we built has only open space and a bathroom. How can I ask for a number....
So the municipality contacted the municipality, and the municipality authorities recommended the construction permission, which required the engineering before writing the plan, and they promised to apply for the next step of the house, so we decided to hire the plan to apply for the construction permission in the municipality.
After that, the municipality approved and then applied for the house number at the headman in the area.
Then... bring the documents from the director back to the municipality and ask for a copy from the district, and then apply the house registration documents to the electricity supply.
And then the time came for us to wait, and we asked for free electricity to enter the building, the first 140 meters free of charge.